Bilbo Solar Farm

  • Size:
    36.6 MW
  • Location:
    Scotland, UK
  • Project owner::
    Lynher Energy

About Bilbo Solar Farm

Bilbo Solar Farm is a 36.6 MW solar farm with adjacent battery energy storage facility in planning. It is located in Aberdeenshire, Scotland.

The site was originally developed by Green Energy International and acquired by Lynher Energy (joint venture between Ethical Power and Napier Park Capital) in July 2022.

Ethical Power completed the due diligence, optimisation and design engineering of the plans as well as the final development stages including obtaining relevant permissions and securing grid connection.

The project is now in construction.

Project timeline

  • 2017
    Site identified by GEI
  • 2019
    Initial site development complete by GEI
  • July 2022
    Lynher Energy Acquires the project
  • January 2024
    Construction begins
  • September 2024
    Successful CfD award in AR6 CfD auction

About Lynher Energy

Lynher Energy is the joint venture established by Napier Park Global Capital and Ethical Power to invest in large-scale solar and battery storage assets in the UK and Europe. The combination of Napier Park’s extensive experience in sponsoring industry-leading joint ventures combined with Ethical Power’s capabilities and knowledge in the development, construction, operation and maintenance of large and complex solar projects offers the ability to develop high-quality, valuable assets while pursuing a long-term goal of reducing carbon consumption and transitioning toward green energy resources.